Winner Inspection Sdn. Bhd. has built a strong reputation since its establishment in 2010, delivering reliable inspection and testing solutions across Malaysia’s oil & gas, petrochemical, and energy sectors. With over 15 years of proven experience, we have successfully supported major projects in Sabah, Sarawak, and Peninsular Malaysia, ensuring compliance with international standards and client specifications..
Clients

Services

Project Experience - Detailed List
| Description of Work | Services | Client (Full) | Client (Primary) | Duration | Start Year | End Year | Value (RM) |
|---|---|---|---|---|---|---|---|
| Provison of NDT Services for Sabah Oil & Gas Terminal (SOGT) at Kimanis, Sabah. | RT/MT/PT/UT/TOFD/ PMI/HT | 1) Samsung Engineering Co. Ltd. 2) Epic Mushtari Eng. SB 3) KNM Petrosab Eng. SB | Samsung Engineering Co. Ltd. | 23 Aug 2011 - Nov 2013 | 2011 | 2013 | RM 1,837,050.00 |
| Provison of NDT Services for Kimanis Power Plant (KPP) Project at Sabah. | RT/UT/MPI/DPT | 1) Synerlitz (Malaysia) SB 2) Equator Engineering SB 3) CTCI (M) SB | Synerlitz (Malaysia) SB | 16 Mar 2012 - 12 Dec 2013 | 2012 | 2013 | RM 1,470,269.00 |
| Provison of NDT for Kimanis Power Plant (KPP) Project Gas Pipe Line at Sabah. | RT/MT/UT | TMM Engineering Sdn Bhd | TMM Engineering Sdn Bhd | 2 Jan 2013 - Dec 2013 | 2013 | 2013 | RM 117,675.00 |
| Provision of NDT Services for SAMUR Project at Sipitang, Sabah. | RT/MT/PT/UT/PMI/ PWHT | 1) Science Tech Solutions SB 2) Ingress Fabricators SB 3) KNM Petrosab Eng. SB 4) Labuan Shipyard Eng. SB | Science Tech Solutions SB | Apr 2013 - Aug 2014 | 2013 | 2014 | RM 1,387,387.00 |
| Provision of NDT Services for SAMUR Project at Sipitang, Sabah. | RT/MT/PT/UT/PMI/ PWHT | 1) Dialog E & C Sdn Bhd 2) Rekind Malaysia Sdn Bhd | Dialog E & C Sdn Bhd | Apr 2013 - Mar 2016 | 2013 | 2016 | RM 4,000,000.00 |
| PCN NDT Inspector - Training & certification | NDT Inspector 4 months course | Sabah Skills & Technology Centre | Sabah Skills & Technology Centre | May 2013 - Aug 2013 | 2013 | 2013 | RM 802,900.00 |
| Provision of NDT & PWHT Services for Merapuh A Project (Offshore) in Bintulu, Sarawak Water. | UT/RT/MT/PT/PWHT | EJ Joint Venture SB | EJ Joint Venture SB | 15 May 2013 - Sept 2013 | 2013 | 2013 | RM 199,173.00 |
| To perform gamma scanning & column scanning for column D301 at PCMSB | Column Scanning | Petronas Chemical Methanol SB Labuan | Petronas Chemical Methanol SB Labuan | 18 - 20 June 2013 | 2013 | 2013 | RM 276,200.00 |
| To supply JIT Inspector for Shutdown at Plant 2, PCMSB | JIT Inspector | Petronas Chemical Methanol SB Labuan | Petronas Chemical Methanol SB Labuan | 5 July 2013 - Feb 2014 | 2013 | 2014 | RM 1,483,681.00 |
| To supply JIT Inspector for Shutdown at Plant 1, PCMSB | JIT Inspector | Petronas Methanol Labuan | Petronas Methanol Labuan | Oct 2013 - Nov 2013 | 2013 | 2013 | RM 141,546.00 |
| To supply JIT Inspector for Maintenance at Plant 1, PCMSB | JIT Inspector | Petronas Methanol Labuan | Petronas Methanol Labuan | 6 - 31 Jan 2014 | 2014 | 2014 | RM 141,546.00 |
| To supply JIT Inspector for ABF 13 Turnaround at Bintulu, Sarawak | JIT Inspector | Asean Bintulu Fertilizer Sdn Bhd | Asean Bintulu Fertilizer Sdn Bhd | 14 Jan 2014 - 5 Apr 2014 | 2014 | 2014 | RM 2,659,419.00 |
| Provison of NDT Services for Pre-Shutdown & Shutdown for Plant 1, PCMSB | RT/MT/UT/PT | Turcomp Engineering Services Sdn Bhd | Turcomp Engineering Services Sdn Bhd | 5 Feb 2014 - 25 Mar 2014 | 2014 | 2014 | RM 316,113.00 |
| To supply JIT Inspector for 15 Turnaround at Plant 1, PCMSB | JIT Inspector | Petronas Chemical Methanol SB Labuan | Petronas Chemical Methanol SB Labuan | 1 Aug 2014 - 26 Oct 2014 | 2014 | 2014 | RM 1,096,161.00 |
| Provison of NDT Services for Dalak Pipeline Project at Sipitang, Sabah and Labuan | RT/MT/UT/PT | PBJV Group Sdn Bhd | PBJV Group Sdn Bhd | 4 Sept 2014 - 20 Feb 2015 | 2014 | 2015 | RM 4,316,477.00 |
| Provison of NDT Services for EPCC of South Acis Satellite (SA-SA) Topsides Facilities For MURPHY'S SK309 SPSA Dev Project in Kuching, Sarawak | RT/ MT / UT | Brooke Dockyard & Engineering Works Corporation | Brooke Dockyard & Engineering Works Corporation | 1 Apr 2015 - 30 Apr 2016 | 2015 | 2016 | RM 688,880.00 |
| Provision of NDT Services at Kimanis Power Plant (KPP) Project in Sabah | RT/ MT / PT / UT / UTTG / HT / PMI | Kimanis Power Sdn Bhd | Kimanis Power Sdn Bhd | 2 Apr 2015 - 22 Jan 2022 | 2015 | 2022 | RM 7,000,000.00 |
| Vendor Development Programme (VDP) | RT/ MT / PT / UT / CRT / UTFD / LRUT / PAUT / ECT / Tube Inspection / MFL / IRIS / TOFD / PMI / Thermography / Boroscope / videoscope / Replica | Petroliam Nasional Berhad (PETRONAS) | Petroliam Nasional Berhad (PETRONAS) | 21 May 2015 - 20 May 2022 | 2015 | 2022 | RM 70,129,933.00 |
| To supply JIT and Scaffolding Inspector for Shutdown 2015 at Plant 2, PCMSB | JIT Inspector / Scaffolding Inspector | Petronas Chemical Methanol SB Labuan | Petronas Chemical Methanol SB Labuan | 27 July - 9 Oct 2015 | 2015 | 2015 | RM 450,000.00 |
| To supply Acoustic Eye for Turnaround 15 at Plant 2, PCMSB | APR | Petronas Chemical Methanol SB Labuan | Petronas Chemical Methanol SB Labuan | 18 Aug - 30 Sept 2015 | 2015 | 2015 | RM 350,000.00 |
| To supply Heat Exchangers Tube Inspection for PC Methanol Plant 2, Turnaround 02 2015 | Tube Inspection | Petronas Chemical Methanol SB Labuan | Petronas Chemical Methanol SB Labuan | 18 Aug - 30 Sept 2015 | 2015 | 2015 | RM 1,568,362.00 |
| To supply In Situ Metallographic Examination Services for PC Methanol Plant 2, Turnaround 02 2015 | Replica Testing | Petronas Chemical Methanol SB Labuan | Petronas Chemical Methanol SB Labuan | 21 Aug - 30 Sept 2015 | 2015 | 2015 | RM 408,715.00 |
| Provision of PWHT Services for PFLNG Air-cooled Heat Exchanger Project (ACHE) | PWHT | Time Temasek Sdn Bhd | Time Temasek Sdn Bhd | 9 Sept - 31 Dec 2015 | 2015 | 2015 | RM 340,717.00 |
| Provision of Basic NDT Services and Replica Team at PSR2 & MG3 TA 2016/16 | UTTM / MPT / Replica Testing | Petronas Chemical Methanol SB Labuan | Petronas Chemical Methanol SB Labuan | 29 Jan - 18 Feb 2016 | 2016 | 2016 | RM 274,690.00 |
| Provision of NDT Services for Petronas Carigali Sdn Bhd | RT/ MT / PT / UT / UTTG / HT / PMI | Petronas Carigali Sdn Bhd | Petronas Carigali Sdn Bhd | 1 July 2016 - 31 July 2022 | 2016 | 2022 | RM 14,000,000.00 |
| Provision of NDT and PWHT Services in Labuan F.T. | RT/ MT / PT / UT / UTTG / PWHT | PBJV Group Sdn Bhd | PBJV Group Sdn Bhd | Sept - Nov 2016 | 2016 | 2016 | RM 135,160.00 |
| Provision of NDT and PWHT Services for Pengerang Project at Johor | RT/ MT / PT / UT / UTTG / HT / PWHT | Technofit Sdn Bhd | Technofit Sdn Bhd | 1 Sept 2016 - 30 Apr 2017 | 2016 | 2017 | RM 1,200,000.00 |
| Provision of NDT Services for SSPC in Sabah and Labuan (VDP Scope) | RT/ MT / PT / UT / UTTG / HT / PMI | Sabah Shell Petroleum Company Ltd | Sabah Shell Petroleum Company Ltd | 13 Sept 2016 - 12 Sept 2022 | 2016 | 2022 | RM 7,300,000.00 |
| Provision of NDT Services for Petronas Chemicals Methanol Sdn Bhd | RT/ MT / PT / UT / UTTG / HT / PMI | Petronas Chemicals Methanol Sdn Bhd | Petronas Chemicals Methanol Sdn Bhd | 18 Dec 2016 - 5 Apr 2022 | 2016 | 2022 | RM 10,000,000.00 |
| Provision of NDT & General Services for KNB | RT/ MT / PT / UT / CRT / UTFD / LRUT / PAUT / ECT / Tube Inspection / MFL / IRIS / TOFD / PMI / Thermography / Boroscope / videoscope / Replica | Repsol Oil & Gas Malaysia Limited | Repsol Oil & Gas Malaysia Limited | 23 Mar 2017 - 17 Sept 2022 | 2017 | 2022 | RM 698,804.29 |
| Provision of NDT Services for KPOC | RT/ MT / PT / UT / UTTG / HT / PWHT | Kebabangan Petroleum Operating Company Sdn Bhd | Kebabangan Petroleum Operating Company Sdn Bhd | 12 Apr 2017 - 11 Apr 2022 | 2017 | 2022 | RM 9,000,000.00 |
| Provision of NDT Services for Murphy Sabah Production Operations | RT/ MT / PT / UT / UTTG / HT / PMI | Murphy Sabah Oil Co., Ltd. | Murphy Sabah Oil Co., Ltd. | 10 Aug 2017 - 9 Aug 2019 | 2017 | 2019 | RM 3,000,000.00 |
| Provision of NDT Services for Pengerang Co-Generation Plant Project at Johor | RT / MT / PT / HT | Siemens Malaysia Sdn Bhd | Siemens Malaysia Sdn Bhd | 1 - 30 Sept 2017 | 2017 | 2017 | RM 76,535.00 |
| Provision of PWHT Services for Pengerang Co-Generation Plant Project at Johor | PWHT | Siemens Malaysia Sdn Bhd | Siemens Malaysia Sdn Bhd | 1 Sept - 30 Nov 2017 | 2017 | 2017 | RM 80,652.00 |
| Provision of NDT Services for Petronas Chemicals Fertiliser Sabah Sdn Bhd | RT/ MT / PT / UT / UTTG / HT / PMI | Petronas Chemicals Fertiliser Sabah Sdn Bhd | Petronas Chemicals Fertiliser Sabah Sdn Bhd | 6 Sept 2017 - 5 Sept 2022 | 2017 | 2022 | RM 7,700,000.00 |
| Provision of PWHT Services for 16th Turnaround at Plant 1, PCMSB | PWHT | Welfield Services Sdn Bhd | Welfield Services Sdn Bhd | 27 Oct - 12 Nov 2017 | 2017 | 2017 | RM 160,182.00 |
| Provision of NDT Services for SEC's New Natural Gas Distribution System Facilities to Lot 15 IZ7, KKIP at Kota Kinabalu, Sabah | RT | I Drill Pipelines Constructions Sdn Bhd | I Drill Pipelines Constructions Sdn Bhd | 9 Nov 2017 - 31 Jan 2018 | 2017 | 2018 | RM 308,664.08 |
| Provision of PWHT Services for Pengerang Co-Generation Plant Project at Johor | PWHT | CN Sixth Engineering (M) Sdn Bhd | CN Sixth Engineering (M) Sdn Bhd | 8 Jan - 31 Mar 2018 | 2018 | 2018 | RM 209,021.20 |
| Provision of Visual Inspection Services for GB1 DOSH Inspection Shutdown at KPP in Sabah | Visual Inspection | Kimanis Power SB | Kimanis Power SB | 12 - 19 Feb 2018 | 2018 | 2018 | RM 51,643.20 |
| To provide NDT Services for GB1 DOSH Inspection Shutdown at KPP in Sabah | UTTG / PT / ECT / IRIS / Replica / Boroscope | Kimanis Power SB | Kimanis Power SB | 16 - 19 Feb 2018 | 2018 | 2018 | RM 209,681.78 |
| Provision of NDT Services at KP 182 Pipeline Replacement at Long Luping, Lawas, Sarawak | RT / MT / UT | TMM Engineering Services Sdn Bhd | TMM Engineering Services Sdn Bhd | 5 Apr - 27 May 2018 | 2018 | 2018 | RM 240,000.00 |
| Provision of NDT & Advance NDT Services for PETRONAS Rapid Project EPC Phase PCU-C3 Unit 3215-Package P-27-Flexi HDPE Plant (Mechanical Works) at Pengerang, Johor | RT/ MT / PT / HT / UTFD / PAUT / PWHT | Sapura Project Services Sdn Bhd | Sapura Project Services Sdn Bhd | 8 Aug 2018 - 22 Feb 2020 | 2018 | 2020 | RM 3,000,000.00 |
| To perform Visual Inspection for Kimanis Power Plant (KPP) at Sabah | Visual Inspection | Kimanis Power Sdn Bhd | Kimanis Power Sdn Bhd | 29 Aug 2018 - 28 Aug 2021 | 2018 | 2021 | RM 5,000,000.00 |
| Provision of NDT & Advance Services for Turcomp | RT / MT / PT / UTFD / UTTG / PAUT | Turcomp Engineering Services Sdn Bhd | Turcomp Engineering Services Sdn Bhd | 31 Dec 2018 - Present | 2018 | 2018 | RM 396,810.28 |
| Provision of PWHT Services for EPCC of PFLNG1 Relocation and Tie-in Project at Labuan F.T | PWHT | Sapura Pinewell Sdn Bhd | Sapura Pinewell Sdn Bhd | 14 - 28 Feb 2019 | 2019 | 2019 | RM 111,321.00 |
| Provision of PWHT & NDT Services at Labuan F.T | PWHT / MT / UT | Manuli Fluiconnecto Pte. Ltd. | Manuli Fluiconnecto Pte. Ltd. | 20 Mar - 11 Apr 2019 | 2019 | 2019 | RM 94,160.00 |
| Term Contract of NDT for Petronas Floating LNG1 (L) Ltd ("works") | CR / RT / Replica / Thermography / PMI / TOFD / IRIS / RFET / ECT / UTFD / LRUT / Phase Array | Petronas Floating LNG 1 (L) Ltd | Petronas Floating LNG 1 (L) Ltd | 25 Mar 2019 - 24 Mar 2022 | 2019 | 2022 | RM 2,079,246.42 |
| Provision of NDT Services at South Furious / Barton in Kota Kinabalu, Sabah Water | RT / MT / PT / UT / UTFD | Dayang Enterprise Sdn Bhd | Dayang Enterprise Sdn Bhd | 1 July - 31 Aug 2019 | 2019 | 2019 | RM 167,342.00 |
| Provision of NDT Services for H-22 at South Furious (Offshore) in Kota Kinabalu, Sabah Water | RT | Dayang Enterprise Sdn Bhd | Dayang Enterprise Sdn Bhd | 1 Feb - 10 Mar 2020 | 2020 | 2020 | RM 70,903.00 |
| Upgrading and Repairing the insfrastructure and facilities and related work on the Bird Park, WP. Labuan | Repair / Maintenance | Perbadanan Labuan | Perbadanan Labuan | 17 Feb - 13 Aug 2020 (extended to 2 Oct 2020 due to MCO) | 2020 | 2020 | RM 724,514.00 |
| Provision of NDT Services at St Joseph Platform (Offshore) in Kota Kinabalu, Sabah Water | RT / MT / PT / UT / UTFD | Dayang Enterprise Sdn Bhd | Dayang Enterprise Sdn Bhd | 1 July - 31 Aug 2020 | 2020 | 2020 | RM 256,155.00 |
| Provision of NDT Services for SJJT-F Post Drill 2020 at ST. Joseph (Offshore) in Kota Kinabalu, Sabah Water | RT / MT / UTFD | Dayang Enterprise Sdn Bhd | Dayang Enterprise Sdn Bhd | 1 - 30 Oct 2020 | 2020 | 2020 | RM 99,993.00 |
| Provision of NDT Services for Kinarut-ERB West Compressor upgrading at Kota Kinabalu, Sabah | RT / UT / PMI / MT | Sapura Pinewell Sdn Bhd | Sapura Pinewell Sdn Bhd | 29 Oct - 31 Dec 2020 | 2020 | 2020 | RM 642,295.00 |
| Provision of NDT Services at ST. Joseph (Offshore) in Kota Kinabalu, Sabah Water | RT / MT / PT / UT | Dayang Enterprise Sdn Bhd | Dayang Enterprise Sdn Bhd | 1 - 30 Nov 2020 | 2020 | 2020 | RM 108,929.00 |
| Term Contract for NDT for Petronas Floating LNG2 (L) Ltd | CR / RT / UTFD / LRUT / Phase Array / IRIS / RFET / ECT / TOFD / PMI / Thermography / Replica Testing | Petronas Floating LNG 2 (L) Ltd | Petronas Floating LNG 2 (L) Ltd | 1 June 2021 - 24 Mar 2022 | 2021 | 2022 | RM 4,000,000.00 |
| Provision of NDT Services for WR 138 SF/BT TMM 2021 at South Furious (Offshore) in Kota Kinabalu, Sabah Water | RT / MT / UTFD | Dayang Enterprise Sdn Bhd | Dayang Enterprise Sdn Bhd | 1 - 31 July 2021 | 2021 | 2021 | RM 107,540.00 |
| Provision of PWHT Services for B11 Compressor Change - out Project (Offshore) | PWHT | Carimin Engineering Services Sdn Bhd | Carimin Engineering Services Sdn Bhd | 1 - 31 Aug 2021 | 2021 | 2021 | RM 191,362.00 |
| Provision of NDT & Advance Services for Carimin | RT / MT / PT / UTFD / UTTG / PAUT / Multitech / HT/ Ferrite | Carimin Engineering Services Sdn Bhd | Carimin Engineering Services Sdn Bhd | 3 Aug 2021 - Present | 2021 | 2021 | RM 1,663,013.46 |
| Provision of NDT Services for BAYAN Development Phase II (Onshore) | RT / UT / MT / PT / PMI / HT / UTTG | Labuan Shipyard & Engineering SB | Labuan Shipyard & Engineering SB | 5 Jan - 19 Dec 2022 | 2022 | 2022 | RM 255,860.00 |
| Provision of NDT & Advance NDT Services for SSGP KP265 at Miri, Sarawak | PAUT / TOFD / UT / MT / PT | TMM Engineering Services Sdn Bhd | TMM Engineering Services Sdn Bhd | 1 - 31 Mar 2022 | 2022 | 2022 | RM 425,680.00 |
| Provision of NDT Services at Perdana Protector (Offshore) in Kota Kinabalu, Sabah Water | RT / MT / PT / UT | Dayang Enterprise Sdn Bhd | Dayang Enterprise Sdn Bhd | 1 Apr - 31 May 2022 | 2022 | 2022 | RM 191,354.00 |
| Provision of NDT Services for KPOC | RT/ MT / PT / UT / UTTG / HT / PWHT | Kebabangan Petroleum Operating Company Sdn Bhd | Kebabangan Petroleum Operating Company Sdn Bhd | 28 Apr 2022 - 27 Oct 2023 | 2022 | 2023 | RM 1,800,000.00 |
| Provision of NDT & Advance NDT Services for May 2022 TA at SAMUR Project in Sipitang, Sabah | RT / PT / UTTM / UTFD / ECT / MFL / PAUT / RFET / C-SCAN / Boroscope / HT / Replica | Petronas Chemicals Fertiliser Sabah Sdn Bhd | Petronas Chemicals Fertiliser Sabah Sdn Bhd | 11 May - 16 June 2022 | 2022 | 2022 | RM 1,992,211.00 |
| Provision of NDT Services for Development Phase 2 at Labuan Shipyard Yard (Onshore) | RT / UT / MT / PT / PMI / HT / FCM | Labuan Shipyard & Engineering Sdn Bhd | Labuan Shipyard & Engineering Sdn Bhd | 1 June 2022 - Present | 2022 | 2022 | RM 319,079.00 |
| One Off Maintenance Work in JKR Quarters under Economic Stimulus Package (ESP) for 2020 WP. Labuan | Maintenance | Jabatan Kerja Raya WP. Labuan | Jabatan Kerja Raya WP. Labuan | 6 July - 22 Nov 2022 | 2022 | 2022 | RM 703,092.63 |
| Provision of NDT Services for Redevelopment Project Gas Phase 2 at BAYAN Platform in Sarawak Water | UT / MPI / HT / RT | Dialog E & C Sdn Bhd | Dialog E & C Sdn Bhd | 14 July 2022 - 10 May 2023 | 2022 | 2023 | RM 781,679.00 |
| Provision of NDT Services for Press Metal at Bintulu, Sarawak | UTTG / Boroscope | Press Metal Bintulu Sdn. Bhd. | Press Metal Bintulu Sdn. Bhd. | 23 Aug 2022 - 23 Jan 2024 | 2022 | 2024 | RM 548,280.00 |
| Provision of NDT Services for KNB 2022 Inspection Campaign at KNDP in Labuan Water | RT/ UT / CVI | Hibiscus Oil & Gas Malaysia Limited | Hibiscus Oil & Gas Malaysia Limited | 1 - 10 Sept 2022 | 2022 | 2022 | RM 327,141.00 |
| Provision of NDT & PWHT Services for Dayang Enterprise Sdn Bhd | RT / PMI / MPI / DPI / Ferrite / Hardness Testing / PWHT | Dayang Enterprise Sdn Bhd | Dayang Enterprise Sdn Bhd | 15 Dec 2022 - Present | 2022 | 2022 | RM 4,112,194.47 |
| Provision of NDT Services for Sapura Pinewell Sdn Bhd | MPI / DPI / RT | Sapura Pinewell Sdn Bhd | Sapura Pinewell Sdn Bhd | 15 Feb 2023 - Present | 2023 | 2023 | RM 67,262.00 |
| Provision of Pan Malaysia Inspection Services - Basic Non-Destructive Test (NDT), Appointment as Panel of Contractor (Downstream - Sabah) | RT/ MT / PT / UT / UTTG / HT / PMI | Petroliam Nasional Berhad (PETRONAS) | Petroliam Nasional Berhad (PETRONAS) | 15 June 2023 - 14 June 2028 | 2023 | 2028 | RM 7,500,000.00 |
| Provision of Pan Malaysia Inspection Services - Basic Non-Destructive Test (NDT), Appointment as Panel of Contractor (Upstream - Sabah & Sarawak) | RT/ MT / PT / UT / UTTG / HT / PMI | Petroliam Nasional Berhad (PETRONAS) | Petroliam Nasional Berhad (PETRONAS) | 15 June 2023 - 14 June 2028 | 2023 | 2028 | RM 8,000,000.00 |
| Provision of Pan Malaysia Inspection Services - Basic Non-Destructive Test (NDT) for PCFSSB | RT/ MT / PT / UT / UTTG / HT / PMI | Petronas Chemicals fertiliser Sabah Sdn Bhd | Petronas Chemicals fertiliser Sabah Sdn Bhd | 15 June 2023 - 14 June 2028 | 2023 | 2028 | RM 2,207,000.00 |
| Provision of Pan Malaysia Inspection Services - Basic Non-Destructive Test (NDT) for Petronas Dagangan Berhad Sabah | UTTG / Abseiling / Visual / Work Leader | Petronas Dagangan Berhad | Petronas Dagangan Berhad | 1 Aug 2023 - 14 June 2028 | 2023 | 2028 | RM 801,400.00 |
| Provision of Pan Malaysia - Basic Non-Destructive Test (NDT) Inspection Services | Senior Insp Coordi / API 510 & 570 / Site Safety Supervisor / Senior General Insp / WI / Irata Lvl 3 / Senior Painting Inspector / RBI Analyst / Senior Lifting Surveyor / Senior NDT Tech | Sarawak Shell Berhad / Sabah Shell Petroleum Company Limited | Sarawak Shell Berhad / Sabah Shell Petroleum Company Limited | 30 Nov 2023 - 29 Nov 2028 | 2023 | 2028 | RM 128,000,000.00 |
| Onshore Non-Destructive Testing (NDT) Services | RT / MT / PT / UTTG / UTFD / HT / PMI / PWHT | Dayang Enterprise Sdn Bhd | Dayang Enterprise Sdn Bhd | 1 Dec 2023 - 31 Dec 2024 | 2023 | 2024 | RM 400,000.00 |
| Offshore Non-Destructive Testing (NDT) Services | MT / PT / RT / UT / HT / PMI | Dayang Enterprise Sdn Bhd | Dayang Enterprise Sdn Bhd | 1 Dec 2023 - 31 Dec 2024 | 2023 | 2024 | RM 1,100,000.00 |
| Provision of 10th Malaysia Inspection Services 3rd Party Inspector | JIT Inspector | Petronas Chemicals Fertiliser Sabah Sdn Bhd | Petronas Chemicals Fertiliser Sabah Sdn Bhd | 30 June 2025 - 7 Sept 2025 | 2025 | 2025 | RM 4,586,025.00 |
| Onshore Non-Destructive Testing (NDT) Services | MT / PT / RT / UT / HT / PMI | Petronas Chemicals Fertiliser Sabah Sdn Bhd | Petronas Chemicals Fertiliser Sabah Sdn Bhd | 21 July 2025 - 7 Sept 2025 | 2025 | 2025 | RM 1,128,709.00 |